Basically, to connect your installation to Glamox Connect you need an Access point as well as a gateway(s) connected to your local installation.
The access point is the one point connected to Glamox Connect. The access point communicates to the gateway(s) on the local network.
Components
Access point - LMS CONNECT RevPi Core 3 8GB
Local gateways to your systems:
Ethernet2Dali (E2D) - LMS E2D VERTEX APC 3 (if you already have it in your installation, you don’t need to add another one)
Wireless Zigbee - LMS CONNECT ZIGBEE GATEWAY PoE
DALI Complete - LMS CONNECT DALI/TCP GATEWAY
24 V power supply(s) - LMS CONNECT 24V 60W POWER
Ethernet switch ports for all access points and gateways - you can use LMS E2D IND SWITCH
Internet connection - you can use LMS E2D REMOTE ACCESS KIT as a GSM gateway
The Access point needs to be connected to 24 V power as well as ethernet connection.
Gateways limits
There is no hard limit to the number of gateways to 1 access point but recommendations are as follows:
Ethernet2Dali - max 25 gateways (one cluster) per access point
Wireless Zigbee - max 10 gateways per access point
DALI Complete - max 8 gateways per access point
The gateways do not require any physical connection to the access point. The Access point communicates over TCP/IP to all connected gateways.