After setting up the emergency groups, you can schedule when the emergency tests for the grouped devices should run. In the last step you can choose the intervals for functional - and duration tests, as well a start time for the schedule.

You must set a start date for the schedule. The schedule will be created with this date as first possible date.
Example: You have a test set for the 1st in every month. If you set the start date as 02.01.20xx, the first execution of that will be 01.02.20xx

...

After setting schedule you will also get a help text writing out how the schedule is interpreted. This will also include the next execution of the test.

...