Basically, to connect your installation to Glamox Connect you need an Access point as well as gateway(s) connected to your local installation.

The access point is the one point connected to Glamox Connect. The access point communicates to the gateway(s) on the local network.

What do you need?

  1. Access point - RevPI

  2. Local gateways:

    1. Ethernet2DALI - LMS E2D VERTEX ApC 3

    2. Wireless Zigbee - LMS CONNECT ZIGBEE GATEWAY PoE

  3. 24V power supply(s) - LMS E2D POWER SUPPLY 24V 30W

  4. Ethernet switch ports for all access points and gateways - LMS E2D IND SWITCH

  5. Internet connection - you can use LMS E2D REMOTE ACCESS KIT as a GSM gateway

Example with multiple DALI gateways connected to Glamox Connect

The Access point needs to be connected to 24 V power as well as ethernet connection. There is no hard limit to the number of gateways to 1 access point, but recommendations are as follows

  • Ethernet2DALI: Max 25 gateways (one cluster) per access point

  • Wireless Zigbee: Max 10 gateways per access point

  • DALI Complete: Max 8 gateways per access point

Ethernet2DALI

Detailed information on the Ethernet2DALI gateway can be found here: https://glamox.atlassian.net/wiki/spaces/E2D

Wireless Zigbee

The Wireless Zigbee gateway requires PoE or 230V power supply adapter, as well an ethernet connection.

DALI complete

The DALI complete gateway has two ports for DALI connection, so you will need 1 gateway per two DALI lines in your installation. The DALI gateway is physically connected to the DALI lines, as well as connected to your local IP network. The DALI gateway needs 24 V mains connection.

The gateways do not require any physical connection to the access point. The Access point communicates over TCP/IP to all connected gateways.