In this chapter, you will get information on how to commission the E2D system. We assume that you have your electrical installation all set up. This means, all vertexes are connected to the power and all DALI devices are connected to proper DALI buses. These requirements were discussed in the previous chapter of the manual.
Before you start
make sure that you have set a static IP on your PC/laptop. The PC and the VERTEX controller have to be in the same network.
check if you have all the necessary contents of the VERTEX kit
in case of remote commissioning, check if Cloud Gateway is powered on and the external antenna is connected
check the connection of Cloud Gateway with VERTEX controllers - they should be connected with the ethernet cable
Commissioning steps
...
The first steps of the commissioning are always required. Only after completing these steps will your system work. If your system includes only emergency lighting, this is all that is required. The next steps allow you to group and commission DALI devices.
Info |
---|
Before you begin read 0. Good practices before commissioning |
First steps
Filter by label (Content by label) | ||||||||
---|---|---|---|---|---|---|---|---|
|
Next steps
Filter by label (Content by label) | ||||||
---|---|---|---|---|---|---|
|